Value chain

Every stage of a data-centre development, and who runs it.

A single land-to-tenant view leaves out the counterparties that run across several stages. This is the full picture — the part Vastra delivers, and the part the acquirer and operator complete after Ready-to-Build handover.

Note: the counterparties named below are worked through using Andhra Pradesh as the example jurisdiction — state agencies such as APIIC, APEPDCL, APTRANSCO, APERC and APEDB — alongside the relevant central bodies. The stages and roles are the same in any market; only the state-level counterparties change.

Vastra · to Ready-to-Build

Land · Power · Water · Connectivity · Approvals · Design and capital

RTB handover (flexible)

Build · Operate · Own

Counterparty

Occupy

Community and land

Rehabilitation and resettlement (R&R), and CSR.

Central government and standards

MeitY, STPI, CEA / CTU, BIS / TEC / STQC, IGBC / LEED.

Risk and assurance

Tier certification, lender's technical advisor, insurance, surety.

Compute and AI demand

GPU supply (NVIDIA) and GPU-cloud platforms.

These counterparties run across several stages and are often left out of a single land-to-tenant view.

Stage one

Securing the site to Ready-to-Build.

The stages we take to Ready-to-Build, the counterparties at each, and our role. Andhra Pradesh is used as the worked example, with its state agencies and the relevant central bodies named at each stage.

StageWhat it coversKey counterpartiesScope
Land and siteSite identification, title, acquisition or allotment, land-use conversion, and resettlement where applicableLandowners and aggregators; APIIC; SEZ and park developers; Revenue Department and Sub-Registrar; R&R and CSR counterparties; survey and title counselIdentify, verify, secure
PowerGrid intake, tariff, open access, renewable or round-the-clock supply, storage, and large-load connectionAPEPDCL; APTRANSCO and SLDC; APERC; CEA and CTU; NREDCAP and APGENCO; IPPs; BESS and HV equipment suppliersDe-risk to a bankable supply position
WaterBulk and industrial supply, treatment, and coastal coolingWater Resources Department; GVMC; APIIC; STP / ZLD and cooling-water vendorsSecure an assured allocation
ConnectivitySubsea cable landing and diverse terrestrial fibreCable landing operators (Airtel, Sify); DoT; fibre and dark-fibre carriersConfirm diverse, export-grade routes
ApprovalsStatutory clearances, incentives, coastal and fire NOCs, and central IT / DC frameworksSIPB and SIPC; ITE&C and APEDB; MeitY and STPI; APPCB; CRZ authority; Fire Services; VMRDA / DTCP; single-desk portal (UPIN)Obtain clearances and incentives
Design and capitalConstruction-ready design, Tier and green certification, project equity and debtEngineering and Tier-certification advisors; IGBC / LEED and BIS / TEC / STQC; owner's engineer and commissioning agent; project-equity investors; lendersArrange, or hand to the acquirer
Stage two

Build, operate and offtake.

After Ready-to-Build handover, the acquirer and operator complete and run the asset. Named firms are the India market set, shown as illustrative of the role.

StageWhat it coversKey counterpartiesScope
BuildCivil and MEP shell (grey space), and IT and network fit-out (white space)Shell and MEP EPC (L&T, Tata Projects, Sterling & Wilson; Blue Star, Voltas); IT infrastructure and systems integration; structured cabling and equipment suppliersAcquirer / operator
OperateFacility operations, maintenance, security, and IT managed servicesDC operators (AdaniConneX, NTT / Nxtra, STT GDC, CtrlS, Yotta, Sify, Equinix); facilities management (JLL, CBRE); physical security; IT managed servicesOperator
Own / acquireFunds, builds and holds the asset from Ready-to-Build handoverInfrastructure investor or hyperscaler: the party that takes the de-risked site and funds the buildAcquirer
Occupy / offtakeAnchor and colocation demand, and the compute that drives itHyperscalers (Google, Microsoft, AWS, Oracle, Meta); GPU-cloud and GPU supply (NVIDIA); global capability centres; enterprise; sovereign cloudTenant

Runs across the chain, often overlooked: Tier certification and assurance; insurance and surety; central government and standards (MeitY, STPI, CEA / CTU, BIS / TEC / STQC, IGBC / LEED). Investors and hyperscalers are the acquirer at RTB handover, and can also be upstream capital and the anchor tenant.

Roles and verified market context shown. Named firms and bodies are illustrative of the role.